GENALTA OWNS AND OPERATES TWO POWER GENERATION FACILITIES AT JUDY CREEK; A 2 MW ORGANIC RANKINE CYCLE AND A 15 MW GAS TURBINE.

Project Name: Judy Creek Simple Cycle      

Project Type: Gas to Power         

Location: Whitecourt, AB

Size: 15 MW              

ISD: Summer 2014

The Judy Creek Simple Cycle Gas facility converts gas into electricity during peak hours.  Remotely operated, the Judy Creek facility adds value to gas that would otherwise be sold to market.

 

Project Name: Judy Creek Organic Rankine Cycle    

Project Type: Waste Heat o Power

Location: Whitecourt, AB               

Size: 2 MW              

In-Service Date: Spring 2013

The Judy Creek Organic Rankine Cycle converts the wasted heat generated from turbine exhaust into 2.2MW of emission-free electricity. The power is used on our client’s site to offset power, delivery, and transmission charges incurred from the utility.  Genalta Power is the design-builder, owner, and operator of this facility.