THE CADOTTE FACILITY, CONSTRUCTED AND COMMISSIONED IN 2012, IS DESIGNED TO GENERATE ELECTRICITY FROM OTHERWISE-FLARED SOUR SOLUTION GAS.

Project Name: Cadotte      

Project Type: Solution Gas to Power        

Location: Peace River, AB

Size: 4 MW              

In-Service Date: Spring 2012

The Cadotte Facility generates a new source of revenue for our partner in Peace River. By diverting gas from flare, we’re generating base load electricity, reducing operating expenses, and improving our client’s environmental performance. The innovative project was granted a patent for its design, and we are proud to say that the Cadotte facility is the first flare gas to power project to earn Greenhouse Gas Offset Credits in Alberta. It is estimated that over the life of the project, the facility will reduce regional emissions by over 240,000 tonnes of CO2e.